6 Mr Sitoh Yih Pin asked the Minister for Transport (a) what is the reason for the delay in completion of the sheltered linkway at Woodleigh Close under the Walk2Ride programme; and (b) what is LTA's estimated date of completion of these works.

Mr Khaw Boon Wan: It was originally estimated that the sheltered linkway at Woodleigh Close would be completed by May 2016. Since then, the Land Transport Authority has found that it needs more time to ensure that the linkway's construction does not affect existing utilities infrastructure and adjacent trees. The expected completion date is now August 2016.