Written Answer to Unanswered Oral Question

Contractor in Case Where There Was Inadequate Oversight of HDB Car Park Patrol and Enforcement as Recorded in FY2025/2026 Auditor-General's Report

Speakers

Transcript

136 Mr Abdul Muhaimin Abdul Malik asked the Minister for National Development with reference to the Auditor-General Office's finding on inadequate oversight of carpark patrol and enforcement by HDB (a) which contractor was found to have discrepancies in service performance; (b) whether the contract remains in force; (c) when the contract is expected to end; and (d) whether the deficiencies identified will lead to HDB selecting another contractor for future services required.

Mr Chee Hong Tat: As reported by the media, the contractor is Certis Cisco Auxiliary Police Force Pte Ltd. The affected contract ended on 31 January 2026.

The Housing and Development Board has commenced recovery of the administrative charges, which includes the full extent of payments made for works not rendered. The lapses will be taken into account in future tenders that Certis Cisco bids for.